Production and installation of pipelines, hydraulic testing, NDT
Project: Pipeline production and installation, hydraulic testing, NDT
Client: LAB SA
Project location: Copenhagen, Denmark
Project Implementation: 2018
Project parameters:
Supply, manufacture and installation of water heating and supply pipelines. Temperature 260 OC, pressure 250 Bar.
Work in progress:
Supply of pipelines and parts;
Production and installation of pipeline preparations (approximately 4500 welds);
Non-destructive testing of pipelines, hydraulic testing, certification
Manufacture and installation of supports.